Concerned Citizens:

CONCERNED CITIZENS:

Please use the below form to make your voice heard with the South Carolina Department of Environmental Services (SCDES)

Name(Required)

Address

If you're a local resident, please let that be known
Please use this space to share any additional thoughts you have regarding the 'Road to Compromise' or the Laurel Hill Parkway. This information will be sent to SC DES.

To:
South Carolina Department of Environmental Services

Re: Highway 41 Corridor Improvements - Construction Stormwater and Coastal Review

I join Smart Growth 41 and other residents in asking the South Carolina Department of Environmental Services to withhold construction stormwater authorization and the related Coastal Zone Consistency determination for the Highway 41 Corridor Improvements Project until the most important site-specific questions are fully answered.

The application describes approximately 5.6 miles of roadway work, 76.9 acres of land disturbance, and 16 stormwater outfalls. It seeks a detention waiver and proposes discharges toward Horlbeck Creek, Mill Creek, Toomer Creek, the Wando River, Copahee Sound, and connected impaired and shellfish-harvesting waters.

This is not a routine construction site. It is a multiyear project involving extensive clearing, grading, bridge work, dewatering, wetland impacts, and construction beside sensitive coastal resources and established neighborhoods.

Residents have raised flooding, drainage, wetland loss, and water quality concerns throughout the public process, including at the 2024 hearings and in written comments submitted in 2024 and 2025. Those comments requested disclosure and independent review of the hydrologic modeling, rainfall assumptions, detention sizing, floodplain data, projected flows, and downstream water quality impacts supporting the project. The current application does not demonstrate that those questions have been resolved.

Several issues remain inadequately addressed:

  1. The application's flooding response requires explanation. The Notice of Intent states that no flooding problems exist downstream of or adjacent to the project. That answer is difficult to reconcile with years of public testimony concerning low-elevation areas, flood-zone crossings, drainage problems, and the effects of filling and grading within Laurel Hill Park. SCDES should require the County to identify the geographic area it considered and disclose the studies, complaint records, field observations, flood maps, and model results supporting that answer.

  2. The detention waiver and hydrologic analysis require a project-specific technical finding. A detention waiver should not be approved through a conclusory statement for a project involving 76.9 acres of disturbance, 16 outfalls, extensive wetland and critical-area impacts, and only three identified permanent water quality or water quantity structures. The record should include the hydrologic and hydraulic models, rainfall assumptions, pre- and post-construction flow comparisons, downstream analysis, effects of lost wetland storage and new impervious surface, and the detention or flow-control alternatives considered.

  3. Each outfall must be evaluated through its complete downstream flow path. Many proposed discharges first enter unnamed tributaries before reaching named creeks, the Wando River, or Copahee Sound. SCDES should identify the drainage area, disturbed acreage, receiving waters, existing impairments, shellfish-harvesting status, anticipated flows, and treatment measures for each outfall. It should also evaluate the combined effects of multiple outfalls entering the same watershed.

    Because these flow paths reach impaired and shellfish-harvesting waters, generic references to standard best management practices are not enough. The record should explain how sediment, turbidity, concrete wash water, fuels, oils, chemicals, and dewatering discharges will be prevented from worsening existing conditions and what monitoring results will trigger immediate corrective action or suspension of work.

  4. The construction controls must be complete, enforceable, and tied to the final project design. Before acting, SCDES should make the full Stormwater Pollution Prevention Plan, grading and drainage plans, construction phasing, stabilization schedule, dewatering controls, inspection requirements, maintenance obligations, and corrective action deadlines available for meaningful review.

    The permit should limit how much land may be disturbed at one time, identify one entity with ultimate responsibility, require inspections after significant rainfall, set firm deadlines for correcting failed controls, and establish a clear process for responding when sediment, runoff, or flooding is observed outside the construction limits. The plan should be revised if another agency changes the alignment, bridges, wetland impacts, drainage design, or construction sequence.

This proceeding does not decide the Army Corps of Engineers' separate Section 404 permit, and I am not asking SCDES to make that federal decision. I am asking SCDES to perform its own review based on complete, current, and publicly reviewable information.

For these reasons, I respectfully request that SCDES withhold approval on the present record, require the missing technical information and site-specific analysis, issue written findings addressing each material issue raised by the public, and impose enforceable conditions sufficient to protect nearby communities, wetlands, creeks, and coastal waters before any authorization is issued.

Future Communication
This field is for validation purposes and should be left unchanged.

lock

The information you provide will not be shared or distributed without your consent. All information is secure and protected with encryption.